Bangalore Metro Yellow Line To Start Operations In January 2025 

3
35000
Representational Image
Representational Image

Bangalore (Metro Rail News): Bangalore Metro Rail Corporation Limited( BMRCL) announced on 5 October that the commencement of operations on Bangalore Metro’s Phase 2 Yellow Line has been delayed. 

BMRCL mentioned that 3 train sets out of 15 trains for Yellow Line will be available by Nov- Dec 2024 and the CMRS inspection will be conducted in the same month leading to operations to begin in January 2025 on Yellow Line. 

The testing with prototype trains provided by China Railway Construction Corporation (CRCC) is under progress. The full fleet of 15 trains is expected to be operational by August 2025. 

Metro Map 2025 Bengaluru City.pdf

Train Specification: 

Total no.of trains for Yellow Line 15 Trains ( 6 coaches each) 
Electrification 750 V DC third rail
Maximum speed 80 km/h
Average speed 34 km/h
Track gauge 1,435 mm (Standard Gauge) 

Bangalore Metro Yellow Line 

Bangalore Metro Yellow Line spans 19.143 km providing connectivity between Rashtreeya Vidyalaya Road ( RV Road) and Bommasandra through 16 elevated stations. 

Stations Covered:

  • Rashtreeya Vidyalaya Road (RV Road)
  • Ragigudda
  •  Jayadeva Hospital
  •  BTM Layout
  •  Central Silk Board
  •  Bommanahalli
  • Hongasandra
  • Kudlu Gate 
  •  Singasandra 
  •  Hosa Road 
  •  Beratena Agrahara 
  •  Electronic City
  •  Infosys Foundation Konappana Agrahara 
  • Huskur Road
  •  Hebbagodi 
  • Bommasandra

Further Updates: 

The rolling stock contract for Bangalore Metro Yellow Line was awarded to CRCC later the contract got cancelled and Titagarh Rail System Limited was awarded the contract. 

Titagarh will be delivering 2 trains every month and is expected to complete the contract of 15 rolling stocks for Yellow Line by August 2025. 

3 COMMENTS

  1. Already hosa road traffic is unbearable. Now this is open with out proprer parking is going to kill that road

  2. Very happy for new line. When you are going to start metro line from Mysore road to jpnaghar 4 th phase via verabdranaghar, PES College hoskerahalli, katriguppe, kamakya, devegowda petrol bunk,kaderenahalli, Banashankari metro station

  3. If this is the case here, I doubt that even the already delayed blue line will take atleast 5 more years.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.