NCRTC Conducts Trial Run Between Meerut South and Shatabdi Nagar RRTS Station

0
505
Trial Run Between Meerut South and Shatabdi Nagar RRTS Station

New Delhi (Metro Rail News): On 9 February 2025, National Capital Regional Transportation Corporation (NCRTC) conducted trial run on an additional 6 km stretch spanning from Meerut South to Shatabdi Nagar in Meerut. 

WhatsApp Image 2025 02 13 at 3.15.04 PM
Image Credit: NCRTC

This 6 km stretch between Meerut South and Shatabdi Nagar features 3 stations in total. The Shatabdi Nagar Station is part of the Delhi-Ghaziabad-Meerut RRTS Project. The remaining 2 stations Partapur and Rithani are a part of Meerut Metro. 

WhatsApp Image 2025 02 13 at 3.15.05 PM
Image Credit: NCRTC

Shatabdi Nagar station in Meerut is the second RRTS station on which both Namo Bharat and the Meerut Metro will operate.

WhatsApp Image 2025 02 13 at 3.15.06 PM
Image Credit: NCRTC
WhatsApp Image 2025 02 13 at 3.15.05 PM 1 1
Image Credit: NCRTC

NCRTC’s Objective Behind the Trial

As the testing phase progresses, NCRTC will undertake thorough evaluations to assess the integrated performance of the train and its coordination with critical subsystems, including track infrastructure, signaling systems, Platform Screen Doors (PSDs), and overhead power supply systems. 

About Delhi – Ghaziabad- Meerut RRTS Corridor 

Currently, the Delhi – Ghaziabad RRTS Corridor is operational between New Ashok Nagar and Meerut South spanning 55 km through 11 stations.   

 Stations  

  •  New Ashok Nagar
  • Anand Vihar
  • Sahibabad 
  • Ghaziabad 
  • Guldhar 
  • Duhai  
  • Duhai Depot 
  • Muradnagar 
  • Modi Nagar South
  • Modi Nagar North 
  • Meerut South

Once this section becomes operational, the Delhi- Ghaziabad-Meerut RRTS corridor section will extend up to 61 km featuring 12 stations. 

Further Updates 

The Meerut Metro project is also progressing rapidly on the other hand. Currently, NCRTC is also conducting trial runs between the Meerut South and Meerut Central. The entry and exit structures are nearly complete while the finishing touches are underway At Partapur and Rithani stations. Furthermore, Platform Screen Doors have been installed till Shatabdi Nagar Station. 

.