Home Latest News TBM Vamika achieves second breakthrough in Lakkasandra Station of Bangalore Metro

TBM Vamika achieves second breakthrough in Lakkasandra Station of Bangalore Metro

This was its second tunnel breakthrough for the southbound tunnel of the 3.655 km Package RT-01 between Rashtriya Military School Station and Dairy Circle South Ramp of the 73.92 km Bangalore Metro Phase 2 project.

0
796
TBM Vamika achieves second breakthrough in Lakkasandra Station of Bangalore Metro
TBM Vamika achieves second breakthrough in Lakkasandra Station of Bangalore Metro

BANGALORE (Metro Rail News): Afcons Infrastructure’s Tunnel Boring Machine S-1260 made a tunnel breakthrough on 12th December at Lakkasandra Station for the 21.386 km Pink Line (Nagawara – Kalena Agrahara) of the Bangalore Metro.

Advertisement1
InnoMetro_2026

TBM S-1260, also known as Vamika. This was its second tunnel breakthrough for the southbound tunnel of the 3.655 km Package RT-01 between Rashtriya Military School Station and Dairy Circle South Ramp of the 73.92 km Bangalore Metro Phase 2 project.

The Herrenknecht earth pressure balance (EPB) machine was commissioned from the South Ramp in June 2021 and travelled 614 metres to Dairy Circle Station in January 2022 to record a “hidden breakthrough.”

After passing through the box of Dairy Circle Station, the machine continued to travel a distance of 747.338 metres to reach Lakkasandra Station.

According to the tunnelling plan, Afcons expected to finish tunnelling on this segment in 243 days; however, they did so in 232 days.

TBM Rudra (S-1259) is working on the same northbound tunnel route, which remains stranded in a garbage dump once a granite quarry.

There is only one more project left for TBM Vamika, a 714.51-meter tunnel towards Langford Town Station that Afcons aims to finish in 157 days.

The most recent BMRCL November newsletter indicates that Phase 2’s tunnelling work (total scope: 21,041m) was about 62.39% finished by October.

A total of 15 out of 26 breakthroughs have been recorded: 5 on Package RT-01 by Afcons, 3 on RT-02 by L&T, 4 on RT-03 by L&T, and 3 on RT-04 by ITD Cementation.