TBM Bhadra of the Bangalore Metro Achieves Breakthrough at K.G Halli 

Date:

Share post:

BANGALORE (Metro Rail News): TBM S-840B or TBM Bhadra of the bangalore metro achieved a breakthrough today. It’s been deployed on the Bangalore Metro’s 21.386 km long Pink Line. 

Assignment 

It has built an 1184 m long northward tunnel from Venkatsehpura to K.G Halli. It has bored at an average rate of 3.3m/ day through hard topographic terrain. It took the TBM  approximately a year or less to construct an 1184 m tunnel on the Pink Line of the bangalore metro running from  Kalena Agrahara to Nagawara.

Launch 

The TBM was commissioned from Venkateshpura Station Southward to Tannery Road in June 2021. Later, it was launched on the  Venkateshpura-K.G Halli Road on February 16, 2023, at the  Venkateshpura underground station. 

TBM Bhadra Dhilip kumar 03

Assignments completed by the TBM 

Total assignments completed by the TBM  with dates are as follows: 

  1. Venkateshpura to Tannery Road (822m): June 2021 – July 2022
  2. Tannery Road to Shadi Mahal TBM Retrieval Shaft (222m): July 2022 – December 2022
  3. Venkateshpura to Kadugondanahalli (1184m): February 2023 – February 2024

Next assignment 

Following this progress, Bhadra will be transported across Kadugondanahalli Station’s enclosure, expected to last between 20 and 45 days. It will commence its fourth and final phase, covering approximately 935 meters towards the southern cut & cover section 1 of Nagawara Station.

Update on Tunnel of the Pink Line 

With this breakthrough, the bangalore metro has achieved a total tunnel construction of length 19,120.70 meters out of a total of 20,992 metres on the 21.26 km long Bangalore Metro’s Pink Line. It can account for approximately 91% of the total work. 

BMRCL aims to complete the tunnelling work on the line by the end of August 2024. 

TBM Bhadra Roopa Pramnik banerjee 01

Pink Line: Kalena Agaraha (formerly Gottigere) – Nagawara

Total Length: 21.386 km (Elevated +  Underground ) 

Covering Stations: 18

Kalena Agrahara (formerly Gottigere), Hulimavu, IIM-Bangalore, JP Nagar 4th Phase, Jayadeva Hospital, Swagath Road Cross, Dairy Circle, Lakkasandra (formerly Mico Industries), Langford Town, Rashtriya Military School (formerly Vellara Road), MG Road, Shivaji Nagar, Cantonment, Pottery Town, Tannery Road, Venkateshpura, Kadugundanahalli (formerly Arabic College) and Nagawara

Status: Under Construction


Discover the endless possibilities of our city’s Metro at InnoMetro, our flagship Expo and Conference. Be an active participant in shaping its future towards a more sustainable tomorrow. Stay informed and join us to take a step towards a brighter future

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.

spot_img

Related articles

Mumbai Metro 3: RDSO Conducts Trials of Rolling Stock on Aqua Line

The work is advancing swiftly on the Aqua Line (Line 3) of the Mumbai Metro. In a recent...

Nagpur Metro Phase 2: 6 Firms Submit Bids for Package C-02

Nagpur (Metro Rail News): On 20 June 2024, Maharashtra Metro Rail Corporation Limited (MAHA METRO) opened technical bids...

Kochi Metro: Afcons Infrastructure Bags Rs. 1141.32 crore Civil Contract of Pink Line

Kochi (Metro Rail News): On 20 June 2024, Afcons Infrastructure bagged a contract worth Rs. 1141.32 to undertake...

Patna Metro: L&T Deploys TBM-1 at Patna University Metro Station

Patna (Metro Rail News): The Patna Metro Phase 1 project is advancing at a rapid pace. Recently,  Larsen...