TBM Adyar Records Breakthrough on Chennai Metro Line 3

0
438
Chennai Metro's TBM Adyar

Chennai (Metro Rail News): Chennai Metro advanced as Larsen & Toubro (L&T)’s TBM Adyaar (S-1326A) achieved its first breakthrough for Package TU-02 at Adyar Junction on Line 3 for Chennai Metro Phase 2 spanning 116.1 km. 

This is the fourth tunnel breakthrough in 12 km Package TU-02 which connects Kellys and Taramani Road Junction stations on Line 3. This entire corridor covers a 45.8 km distance through 49  stations (20 elevated & 29 underground). 

1739511163919
Image Credit: Kaleidoscope

TBM Adyar ( S-1326A) 

TBM S-1326A, nicknamed TBM Adyar is a 100m long Ø6.65m Herrenknecht earth pressure balance (EPB) machine. IN July 2022, TBM Adyar passed factory acceptance tests (FAT) at Herrenknecht’s Alinjivakkam facility. 

1739457048387
Image credit: Debashis Tantubai 

For its first assignment (current), TBM Adyar was deployed at  Greenways Road Station in April 2023 and it constructed a 1218 m tunnel for the upline. 

The TBM achieved a breakthrough in 22 months due to difficult mixed geological conditions. TBM Adyar constructed an approx 300 m tunnel below the Adyar River. 

TBM Adyar is 1 of 8 machines commissioned by L&T for constructing twin tunnels from Kellys to Taramani Road Junction stations spanning 12 km ( total 24 km). 

Package TU-02 

L&T bagged Package TU-02 from Chennai Metro Rail Ltd. (CMRL) at  Rs. 2385 crore in May 2021 with a 42-month deadline.

The scope of work under this Package includes the construction of twin tunnels between Kellys and Taramani Road Junction. In addition, the contract also includes the construction of diaphragm walls, entry/exit structures of Chetpet Station, Royapettah Government Hospital Station, Thiruvanmiyu Station, and part diaphragm wall of Greenways Road Station, including launching and retrieval shafts at the above stations.

Chennai Metro Line-3 Tunnel Breakthroughs

With this breakthrough, a total of 10 breakthroughs have been achieved so far for Line 3.

South-Side (L&T – Package TU-02: Kellys to Taramani Road Junction)

Month & YearTBM Name (ID)Breakthrough LocationTunnel Length (m)
August 2024Siruvani (DZ1040)Sterling Road703
September 2024Kaveri (S-1327A)Adyar Junction1228
October 2024Palar (DZ1041)Sterling Road700
February 2025Adyar (S-1326A)Adyar Junction1218

North-Side (Tata Projects – Package TU-01: Madhavaram to Kellys)

Month & YearTBM Name (ID)Breakthrough LocationTunnel Length (m)
June 2023Anaimalai (S98)Venugopal Nagar415
August 2023Nilgiri (S96)Madhavaram High Road1400
September 2023Servarayan (S99)Venugopal Nagar415
November 2023Podhigai (S97)Madhavaram High Road1400
June 2024Anaimalai (S98)Otteri Station925
August 2024Kolli (S81B)Otteri Station903