Delhi (Metro Rail News): Delhi Metro Rail Corporation (DMRC) has announced SS.SS Construction Pvt. Ltd. as the lowest bidder for the architectural finishing contract of 4 stations of Delhi Metro Phase 4’s Golden Line which spans 23.622 km from Aerocity to Tuglakabad.
DMRC Brief Scope of Work: Comprehensive Architectural Finishing Works at Four Underground stations namely Aerocity, Mahipalpur, Vasant Kunj and Kishangarh station on Aerocity-Tughlakabad corridor of Phase-IV of Delhi MRTS.
Contract Details
- Contract Amount: INR 67.73 Cr
- Contract Date: 20 Mar 2025
- Contract Duration: 730 days
Bidding Process
DMRC floated a tender for this contract and 9 firms submitted bids for this work of which the bids of Ghaziabad Mechfab Pvt. Ltd. and Premco Rail Engineers Limited were disqualified in the technical evaluation due to non-compliance with the tender’s terms and conditions.
Technical bids were opened on 11 February 2025. On 20 March 2025, financial bids were opened to reveal that SS.SS Construction was the lowest bidder for the contract.
Financial Bid Value
Bidder Name | Bid Value |
SS.SS Constructions Pvt. Ltd | ₹ 67.7 Cr |
Quality Buildcon Private Limited | ₹ 72.5 Cr |
M/S B. Rai Construction Company | ₹ 72.8 Cr |
Godrej and Boyce Manufacturing Company Limited | ₹ 75.2 Cr |
M/S Garg Builders | ₹ 75.9 Cr |
NS Associates Pvt Ltd | ₹ 76.2 Cr |
MIA Construction Pvt Ltd | ₹ 76.5 Cr |
Contracts Scope of Work
The contract’s scope of work includes the architectural finishing work of 4 stations of Delhi Metro Phase 4’s Golden Line
Stations:
- Aerocity
- Mahipalpur
- Vasant Kunj
- Kishangarh station