Titagarh Rail Receives LoA for Rolling Stock Contract of Mumbai Metro Line 5 

0
442
Mumbai Metro

MUMBAI (Metro Rail News): Titagarh Rail Systems Limited has received a Letter of Acceptance (LoA) from Mumbai Metropolitan Region Development Authority (MMRDA) for the design, manufacture, supply, and commissioning of 132 metro coaches, along with associated systems, for the Mumbai Metro Line 5 project. 

The Line 5 of Mumbai Metro spans 24.90 km Thane to Bhiwandi through 15 stations. The Line 5 of Mumbai Metro Project will be implemented in 2 phases. 

Phase Route 
Phase 1Kapur Bawdi – Kasheli – Dhamankar Naka
Phase 2Dhamankar Naka – Bhiwandi – Kalyan APMC
NOTE@4x 1

MMRDA floated a tender for this contract in 2024 with a completion deadline of 1825 days. Technical bids were opened on 17 December 2024 announcing that 3 firms have submitted bids for the contract. On 24 June 2025 the technical evaluation of the submitted bids occurred; however during the technical evaluation round one firm bid was rejected.

On 24 June 2024, financial bids were opened for the technically qualified bidders. The financial evaluation of the submitted bids occurred on 10 Nov 2025. However, during the financial evaluation round one firm bid was also rejected announcing Titagarh Rail Systems as the lowest bidder for the contract. On the same day, the company received LoA from the MMRDA. 

Financial Bid Values 

Firm Bid Value 
Titagarh Rail Systems Limited₹ 2481 Cr 
Larsen & Toubro Limited₹ 2994 Cr 

Contract Scope of Work: Design, Manufacture, Supply, Installation, Integration, Testing and Commissioning of Rolling Stock, Communication based Signalling & Train Control, Telecommunication, Platform Screen Doors Systems and Depot Machinery & Plant including 5 years of Comprehensive Maintenance after 2 years of Defect Liability Maintenance Period for Mumbai Metro Line 5. 

According to the tender schedule, the delivery timeline for Mumbai Metro Line 5 has been structured in two stages corresponding to the project’s phases.

PhaseTrain Type / BatchDelivery Week (from Contract Signing)Approx. TimeframeNumber of Trains
Phase 1Prototype TrainWeek 561.1 years1
Phase 1Next BatchWeek 781.5 years2
Phase 1Subsequent BatchWeek 961.85 years9
Phase 2First BatchWeek 1803.45 years2
Phase 2Final BatchWeek 1963.75 years8

Witness the innovations & AI- powered solutions in railway & metro systems from over 200 exhibitors at the 6th edition of InnoMetro. Join India’s dedicated show for the rail transit sector which is going to be held on 21-22 May 2026 at Bharat Mandapam, New Delhi. 

Register now: https://innometro.com/visitor-registration/

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.