Indore Metro Advances With Completion Of Pier Foundation On Super Corridor

0
406
Pier Formation completed for Indore Metro

Indore(Metro Rail News): Indore Metro project advanced as URC has finished casting all 142 open foundations and 235 pile caps foundations for the Yellow Line. 

Recently, URC Construction, on a subcontract from Rail Vikas Nigam Ltd. (RVNL), has finally finished casting all 377 pier foundations for Package IN-03 for the 33.53 km Indore Metro Phase 1 project. 

The final foundation of the package for Pier P831 is situated between the Super Corridor 1 and Super Corridor 2 stations.

Package IN-03

Rail Vikas Nigam Ltd. (RVNL) Bagged package IN-03 contract from MPMRCL with an estimated cost of Rs. 1034 crore for Indore Metro’s Yellow Line. Package IN-03 spans 10.927 km, connecting MR10 Road station to Gandhi Nagar stations with a 2.32-year deadline. 

Later, Rail Vikas Nigam Ltd. (RVNL) subcontracted its construction work to URC Construction.

The URC’s scope of work includes the 575m depot line and construction of 9 elevated stations:

  • Gandhi Nagar
  • Super Corridor 6
  • Super Corridor 5
  •  Super Corridor 4
  •  Super Corridor 3
  •  Super Corridor 2
  • Super Corridor 1
  • Bhawarsala Square
  • MR 10 Road

In March 2024, URC completed the casting of all 3302 segments for its viaduct near TCS Chauraha. Furthermore, In September 2023, MPMRCL started the trial runs on a 5.8 km section of IN-03 between Gandhi Nagar Depot and Super Corridor-3 stations. 

 