Mumbai Metro 3: MMRC completes nearly 100% Breakthrough

0
642
Image for representation only.

MUMBAI (Metro Rail News): The Mumbai Metro Rail Corporation (MMRC) has said that it is only nine more breakthroughs away from achieving 100% tunnelling for Mumbai Metro 3 project. Once it completes nine more breakthroughs, it will complete the tunnelling. MMRC said that it has achieved 32 breakthroughs, a length of about 48-km out of the total length of 54.5-km.
“MMRC is only nine more breakthroughs away from achieving 100% tunnelling. The remaining nine breakthroughs will be achieved in package Nos. 1, 3, 4, and 6,” the Metro Corporation said in a statement.

Subodh Gupta, Director (Projects), MMRC said that the tunnelling process in Mumbai is extremely challenging as the alignment passes through densely populated parts.

“Tunnelling in Mumbai is extremely challenging as the alignment passes through densely populated and congested parts of the city. In addition, there are high-rise, heritage, and dilapidated buildings; flyovers, metro viaducts, and railway lines in close proximity. The entire alignment passes through rocky strata. To achieve this task 17 TBMs were working simultaneously at one stage”, He said. Recently, MMRC achieved a 32nd breakthrough of the 1.10-km long tunnel from Siddhivinayak north shaft to Dadar Metro Station.
The overall progress of Dadar Metro Station is 61%. Package-4, which consists of Dadar, Siddhivinayak, and Shitladevi Metro Stations, showcases an overall 94% tunnelling progress and 95% of the excavation work.