L&T Receives LoA for Package CA-234 of Mumbai Metro Line 4 

0
300
Mumbai Metro
Representational Image

MUMBAI (Metro Rail News): Larsen & Toubro (L&T) has received a Letter of Acceptance (LoA) from Mumbai Metropolitan Region Development Authority (MMRDA) for the Package CA-234 of f Line 4 & Line 4A of Mumbai Metro which spans 35.2 km connecting Wadala- Kasarvadavali – Gaimukh.

LOA CA 234 copy

In February 2024, MMRDA re-invited for this contract at an estimated cost of Rs.4279.49 crores and 3723 days deadline. On 18 November 2024 technical bids were opened to announce that only 2 firms had submitted bids for the contract. Technical evaluation of the submitted bids took place on 14 Feb 2025. 

The financial bids for the contract were opened on 14 Feb. The financial evaluation of the bids occurred on 19 September, however during the financial evaluation round one firm’s bid got rejected announcing L&T as the lowest bidder for the contract. 

Financial Bid Values 

Firm Bid Value 
Larsen & Toubro₹ 4788 Cr
NCC Limited₹ 5115 Cr

Contact Details

L&T will be responsible for supplying the 5 major systems under this contract. The systems have mentioned below: 

  •  Supplying rolling stock (39 trains (234 coaches) consisting of 6 coaches)
  •  CBTC signaling & train control (S&T)
  • Telecommunication System 
  • Platform screen doors (PSDs)
  • Depot machinery & plant (M&P) for Mogharpada Depot.

MMRDA’s Brief Scope: Design, Manufacture, Supply, Installation, Integration, Testing and Commissioning of Rolling Stock, Communication Based Signaling & Train Control, Telecommunication, Platform Screen Doors Systems, and Depot Machinery & Plant including 15 Years of Comprehensive Maintenance After 2 Years of Defect Liability Maintenance Period of Line 4 and Extension Corridor (4A) [Wadala – Kasarvadavali – Gaimukh] of Mumbai Metro Rail Project of MMRDA.

As per the tender’s schedule, the 39 trainset has to be delivered according to the timeline mentioned below: 

Batch No.Number of TrainsDelivery Timeline (Weeks from Contract Signing)Delivery Timeline (Years & Months)
1st Batch1 Prototype TrainWeek 521 Year
2nd Batch9 TrainsWeek 701 Year 4 Months
3rd Batch10 TrainsWeek 881 Year 8 Months
4th Batch10 TrainsWeek 1042 Years
5th Batch9 TrainsWeek 1122 Years 2 Months

To get real-time updates on metro and railway tenders, join our WhatsApp  Community:https://chat.whatsapp.com/GP8MIGQ7fP6Eapgbm3d8og?mode=ems_copy_c

Building on a decade of trust, Metro Rail News is pleased to announce the Metro Rail News Awards to recognise organisations and leaders for their outstanding contributions to the rail transit industry. The awards will be presented across 30+ categories, with the ceremony scheduled for 19 September in New Delhi.

Get Recognised for Your Contribution & Innovations – Nominate Now

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.