KPIL Deploys 1st TBM For Underground Section of Kanpur Metro Line 2

0
138
Kanpur Metro

Kanpur (Metro Rail News): Kalpataru Projects International Ltd. (KPIL) – Gulermak deployed their first TBM S-1408A at Rawatpur station of Kanpur Metro’s Line 2 spanning 8.38 km from agriculture university to Barra 8 under package KNPCC-11 on 15 October.

GZ8CNhHXEAAH1GL 1 1

TBM S-1408A

GZ8CNhEWoAAT6bE 1 1

TBM S-1408A, nicknamed TBM Gomati, is the first of two TBM machines for the underground Package KNPCC-11, which connects the Agriculture Depot to the Double Pullia Ramp.

TBM Gomati is the fifth TBM to be deployed for constructing the 32.385 km Kanpur Metro Phase 1 project’s underground twin tunnels.

TBM Gomati will complete the following Assignments for Line 2 of Kanpur Metro:

First assignmentRawatpur station – ramp at Agricultural University 622m Tunnel
Second assignment Rawatpur station- Kakadeo station772m Tunnel. 
Third assignment Kakadeo Station -Double Pullia Station 1005m Tunnel 

Package KNPCC-11

KPIL – Gulermak JV secured Rs. 762.50 crore package KNPCC-11 from Uttar Pradesh Metro Rail Corporation (UPMRC) for  Line 2’s underground section from Agriculture Depot to Double Pullia Ramp spanning 4.08 km in December 2023 with a 30 months deadline.

Package KNPCC-11’s scope of work includes the construction of twin tunnels from the Agriculture Depot to the Double Pullia Ramp and 3 underground stations.

Stations: 

  •  Rawatpur
  • Kakadeo 
  • Double Pullia