First Metro Train Trials Conducted Between GNLU and GIFT CITY Stretch of the Ahmedabad Metro

Upon completion of trials, the Commissioner for Metro Rail Safety will conduct inspections from May to June, paving the way for the planned commencement of metro rail services by June.

0
2745
First Metro Train Trials of Ahmedabad Metro Conducted Between GNLU and GIFT CITY
First Metro Train Trials of Ahmedabad Metro Conducted Between GNLU and GIFT CITY

AHMEDABAD (Metro Rail News): On Sunday, March 10, the first metro train trials were conducted between GNLU and the GIFT CITY link. 

GNLU-GIFT City Stretch 

It is a 5.42 km Branch Line originating from the original  Phase 2 of the Red Line running from Koteshwar Road to Mahatma Mandir. 

It is worth mentioning that this project extends from Narendra Modi Stadium to Mahatma Mandir and GIFT City. It spans 28 km and has 22 stations, of which 21 km of the priority area, from Motera Stadium to Sector 1 and from GNLU to GIFT City, has been planned in a phased manner.

Extended Trials 

The trials for the remaining stretch will be postponed even after the general elections are announced. The next trial of the metro service would be conducted on the Kota-Motera section of the Red Line. 

Trials Ahmedabad metro 02

CMRS Inspection 

After the trials are completed, Commissioner Metro Rail Safety will be moved for inspection, which will take place from May to June. Metro rail services are planned to start by June. 

A Tale of Milestones 

According to metro officials, the entire stretch leading up to Mahatma Mandir is expected to be completed by year-end. The Thaltej to Thaltej Gam section is also slated for completion within the same timeframe. Following the elections, plans are being made to inaugurate the Sabarmati metro station.

Ahmedabad Metro 

A detailed overview of Ahmedabad Metro has been provided below: 

LinePhase-1Phase-2Total Length
Blue Line21.16 km21.16 km
Red LineMain Line18.87 km22.84 km41.71 km
Branch Line5.42 km5.42 km
Total Length40.03 km28.26 km68.29 km

Current Status

Trials Ahmedabad metro 05
Line First OperationalLast ExtensionNumber of operational stationsOperational length
Blue Line4 March 201930 September 202216 (except Thaltej Gam and Kankaria East)19.76 km 
Red Line30 September 2022N/A14 (except Sabarmati Railway station)18.87 km
Total29 (with Old High Court interchange)38.63 km

Discover the endless possibilities of our city’s Metro at InnoMetro, our flagship Expo and Conference. Be an active participant in shaping its future towards a more sustainable tomorrow. Stay informed and join us to take a step towards a brighter future.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.