Bullet Train Project | Shreedharan says, Not right time for bullet train in India

1
395

Former Delhi Metro Chief Dr E Sreedharan today said that he was not in favour of bullet train at present, instead emphasised on the need for the Indian Railways to improve the existing facilities.

“This is not the right time for bullet train in the country but there was a need for improving existing facilities, speed, infrastructure and comforts of passengers,” Sreedharan, also known as the ‘Metro Man’ for developing the vibrant Delhi Metro, said in an informal interaction with reporters on sidelines of a function here.

He said the Railways should concentrate on betterment of the existing facilities at the outset and think of bullet train later.

“May be after eight to 10 years, we may require bullet train,” Sreedharan said.
buy prednisone generic infoblobuy.com/prednisone.html over the counter

To a query on the proposed bullet train between Mumbai and Ahmedabad, Sreedharan, who had spent about 36 years with Railways, expressed his satisfaction over the progress of the Nagpur Metro Rail project.

The Nagpur metro project, he said, was using a new technology where the via duct will be of 8.5 metres against the 10 metres in other Metro Rails across the country.

Earlier, at the first foundation day programme of Nagpur Metro Rail, Sreedharan said the project should be completed on time and it should be affordable to the users, since it was a public transport.

“If you don’t complete the project within the time frame, the cost will escalate Rs 50 lakhs per day. When the detailed Project Report of Delhi Metro was drafted, the completion target was given 10 years but we finished in seven years and three months, which was a record, thereby saving a huge revenue,” he said.

Educate the public and users about the utility and engage them so that there are no inordinate delays in execution, he said, emphasising on evolving a work culture among employees and staff to inculcate a ‘sense of integrity’.

Citing example of Delhi, he said a run of 65 kms Metro Rail reduced congestion on road traffic as about 35,000 cars were off roads and Rs 3 lakh crore was saved on fossil fuel.

Managing Director of Nagpur Metro Brajesh Dixit, Divisional Commissioner Anup Kumar and Municipal Commissioner Shrawan Hardikar were also present on the occasion.

1 COMMENT

  1. Mr.sri dharan is absolutely right. An xpert’s advice 2b considered. Problem is that PM is keen to start from his native place AHMEDABAD. 2nd point luks like it’s a FORCED project 2 impliment in a hurry n PM has settled the deal. Prose n cons have taken a back seat. Thus suspense prevails on the x chequer. Rlys xisting infastructure is sure 2 get a beating n safety measure n tracks R left 2 GOD in protecting the poor passengers. PM is xpert in taking RISK.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

This site uses Akismet to reduce spam. Learn how your comment data is processed.