Bengaluru (Metro Rail News): The Bengaluru Suburban Rail project (BSRP) advanced as NCC Ltd. was awarded Package C2-A by Karnataka’s Rail Infrastructure Development Company (K-RIDE) at Rs. 501.25 crore.
In June 2024, K-Ride floated a tender for Package C2-A with a 2 years deadline. On September 4, technical bids were opened revealing 3 bidders for the package. On October 30, financial bids were opened revealing that NCC was the lowest bidder for the contract.
Final Contract Value: Rs. 501,25,26,713 (including GST)

Scope of Work
The scope of work under Package C2-A includes the construction of 8 stations on Corridor 2 (Mallige Line) spanning 25.57 km from Benniganahalli to Chikkabanavara through 12 stations.
Stations
Stations | Type |
Benniganahalli | Interchange station |
Kasturi Nagar | At- grade station |
Seva Nagar | At- grade station |
Banaswadi | At- grade station |
Nagawara | At- grade station |
Kanaka Nagar | Elevated station |
Hebbal | Elevated station |
Mathikere | Elevated station |
The scope of work of Package C2-A also includes systems installation work such as electrical & mechanical (E&M), pre-engineered building (PEB) roof, and architectural finishing work.
Further Information
- Under Package C2 B, the construction of the other 4 stations ( Yeswanthpur, Shettyhalli, Mydarahalli and Chikkabanavara ) of corridor 2 will be carried out.
- In December, KPC Projects and URC Construction bid to construct the line’s Soladevanahalli Depot.