Bhubaneswar (Metro Rail News): On 8 August, Delhi Metro Rail Corporation (DMRC) issued a Letter of Acceptance (LOA) to Ranjit Buildcon Ltd. (RBL) to carry out the construction under package BBC-03 of the Bhubaneswar Metro Phase 1 project. The contract has been awarded at Rs 561.21 crore.

Package BBC-03

This 7.122 km long package falls on the southern end of 26 km long Corridor 1. It will connect Capital Hospital to Acharya Vihar Square through 6 elevated stations. The stations are:

  1. Capital Hospital
  2. Bapuji Nagar
  3. Bhubaneswar Railway Station
  4. Ram Mandir Square
  5. Vani Vihar and 
  6. Acharya Vihar Square

This is the first of three civil packages (BBC-03, BBC-04, and BBC-05) to receive LOA from DMRC. The contract has a 36-month deadline, and the state government will bear its cost.

Final Contract Value: ₹561.22 crore (including GST and taxes)

Bidding Process

  1. Bid invitation: In March 2024, DMRC called for bids for Package BBC-03, which had an estimated cost of Rs. 630.65 crore and a 3-year (36-month) deadline. 
  2. Opening of Technical Bids: On 19 June, technical bids were opened, and 12 bidders were identified for Package BBC-03. Subsequently, DMRC revealed the financial bids of technically qualified bidders, which can be seen here.

Work Scope of BBC-03

Under this package, Ranjit Buildcon will design and construct an elevated viaduct and 6 elevated stations, as mentioned above, for the Bhubaneswar Metro project. 

This will be Ranjit Buildcon’s third metro project, following their work on the Ahmedabad Metro and Surat Metro projects.

route-map-Bhubaneswar-Metro
Ranjit Buildcon Receives LOA for Bhubaneswar Metro’s BBC-3 Contract 2

Bhubaneswar Metro

On January 1, 2024, Naveen Patnaik, former Chief Minister of Odisha, laid the foundation stone for the Bhubaneswar Metro project. Phase 1 of the project features a 26 km corridor connecting Trisulia Square to Biju Patnaik Airport, with 20 elevated stations. The project is progressing rapidly, and construction activities are set to begin soon.