Bangalore (Metro Rail News): Bangalore Metro Rail Corporation (BMRCL) has invited bids for 2 architectural finishing contracts for Bangalore Metro Phase 2B.
Contract 1
Tender Details
Opening Date | 28 Mar 2025 |
Closing Date | 12 May 2025 |
Estimated Cost of Work | INR 77.12 Crores |
Completion Period of Work | 16 Months |
Pre-Bid Meeting | 19.04.2025 |
Date of the opening of Tender (Technical Bid) | 13.05.2025 at 4.30 PM |
EMD | ₹ 77,12,000 |
Scope of Work
Contract 1 includes the architectural finishing work for 5 elevated stations of Package 2 and one elevated station of Package 3 of Bangalore Metro Phase 2B.
Stations
- Hebbal
- Kodigehalli
- Jakkur Cross
- Yelahanka
- Bagalur Cross
- Doddajala
BMRCL Brief Scope of Work: “Architectural Finishing and Public Health Engineering Works for 6 Elevated Stations viz, Hebbal, Kodigehalli, Jakkur Cross, Yelahanka, Bagalur Cross of Package-2 and Doddajala of Package-3, in Phase 2B line of Bangalore Metro Rail Project”
About Packages 2& 3
Package 2: In 2021, NCC Ltd. bagged the civil construction Package 2 of Bangalore Metro Phase 2B. The scope of work under this package includes the Construction of an 11.678 km viaduct and 5 stations from Hebal to Bagalur Cross.
Package 3: In 2021, NCC Ltd. bagged the civil construction Package 2 of Bangalore Metro Phase 2B. The scope of work under this package includes the Construction of 15.011 km of viaduct and 2 stations at Bettahalasuru and Doddajala.
Contract 2
Tender Details
Opening Date | 28 Mar 2025 |
Closing Date | 12 May 2025 |
Estimated Cost of Work | INR 99.96 Crores |
Completion Period of Work | 16 Months |
Pre-Bid Meeting | 19.04.2025 |
Date of the opening of Tender (Technical Bid) | 13.05.2025 |
EMD | ₹ 99,96,000 |
Scope of Work
The contract 2 includes the architectural finishing work for 8 elevated stations of Package 1 of Bangalore Metro Phase 2B.
Stations
- Kasturi Nagar
- Horamavu
- HRBR Layout
- Kalyan Nagar
- HBR Layout
- Nagawara
- Veeranna palya
- Kempapura
BMRCL Brief Scope of Work:“ Architectural Finishing and Public Health Engineering Works for 8 Elevated Stations viz, Kasturi Nagar, Horamavu, HRBR Layout, Kalyan Nagar, HBR Layout, Nagawara, Veeranna palya, Kempapura of Package-1, in Phase 2B line of Bangalore Metro Rail Project”.
About Bangalore Metro Phase 2B
The Bangalore Metro Phase 2B is an under-construction “airport-link” section of the Blue Line, which spans 37 km from Bengaluru city to Kempegowda International Airport (KIAL) in Devanahalli through 17 stations.